Assembling of the Force

Thursday, 23 July 2015

We are continuing working In Section 2 St. Petersburg Island Kanonerskiy.
LMV is mounting  the Derrick Crane with the lifting capacity of up to 600 tonn.

Our team of 10 high skilled technicians posted at the Russian construction site to perform the delicate and technically difficult installation.
Today was Installed the fifth wheel of total weight of 25 tonn.
Completing the installation and commissioning of the derrick, the crane will be capable of lifting blocks of Double Bridge (Double Deck) maximum weight of 600 tonn.

Alexandr Gomon

Progect Manager, Kanonersky Island Site supervisor

LMV Russia
VCS Montazh