Works report from Krestovsky Island!

Четверг, 30 апреля 2015

At the End of April by VCS have been completed in the Krestovskij Island assembly works of three spans total weight 3000 tonnes.

It concerns Heavy Lifting of one entire span of total length of 100 meters with simultaneous use of two crawler cranes by capacity of 350 tonnes each.

Alexandr Gomon

Progect Manager, Kanonersky Island Site supervisor

LMV Russia
VCS Montazh