EXPO 2015, Theatre

EXPO 2015, Theatre
  • Milan, Italy
  • 2014 / Complete
  • 390 tons
  • 1 500 000

Client: Con.EXPO
Duration of steel structure assembly: 30 days
Total roof covered area: 2200 sqm

Expo 2015 has been held in Milan between 1 May and 31 October 2015. The Open Air Theatre was a principal building for events, musical performances, citizen meetings and one of the few structures that has not be dismantled at the EXPO conclusion. 2500 bolt connections with tubes were used for the whole structure.

supervising LMSteel

productionconstructionsupervising LMV S.p.A.

Open Air Theatre was one of the main tourist attractions on the universal Exposition of…
The LMV group project will not be dismantled after the closing of Expo